On the afternoon of December 30, 2025, a light slush covered Technology Drive near Flying Cloud Drive, along with the Costco and Asia Mall parking lots. Snow sat on the visors over the new light-rail flashers, and the crossing gates were standing at ease, according to Eden Prairie Local News. Test cars had started crossing there a few months earlier, in October.
Most of Eden Prairie now knows the date. Metro Transit says passengers can ride the extended METRO Green Line starting June 12, 2027, a date announced on September 26, 2026 at Louisiana Avenue Station in St. Louis Park. The date doesn't explain what goes on in the meantime. The tracks, bridges and platforms are finished. Between now and June, the line will mostly show itself at a handful of street crossings, where the gates come down for trains that carry no passengers.
The construction contract is closed, and the systems work is what's left
The line has looked finished for a while. Last winter, project director Jim Alexander told the Corridor Management Committee, "The challenge is that it kind of looks like it's done, but it's not done," as reported by Eden Prairie Local News. In December 2025, 95% of civil construction was complete and 85% of the operating system was installed.
Those numbers have since moved. At the October 26 Minnetonka City Council meeting, Alexander said the civil construction contract was wrapped up on October 15, according to the Sun Sailor. "What's left is really the Systems elements," he told the council, naming communications, traction power and the signalization of the system.
That systems work is bigger than it sounds. Alexander told the same meeting that more than 7,500 devices along the 14.5 miles and 16 stations need testing, both to confirm they communicate with one another and to confirm they reach the Rail Control Center in Minneapolis. Earlier in the year, he estimated more than 1,500 train runs to test switches, power delivery, clearances, communications and crossing signals, with every operation tested and retested day and night, in all seasonal weather. The winter now starting counts as part of that test, because the line has to work in Minnesota winter weather before it opens.
The road to June 12, and where it stands now
Here's the sequence project staff have laid out. The first two steps are already finished, and the rest is still ahead, as reported by the Sun Sailor and Eden Prairie Local News:
- October 15, 2026. The civil construction contract is finished.
- Systems Integration Testing, Phase I. Complete from Louisiana Avenue to SouthWest Station in Eden Prairie. This phase covered track alignment and clearances, roadway and pedestrian systems, overhead power, signals and train control, and communications.
- Phase II. Underway as of late October.
- Phase III. The final phase, expected to wrap up in December.
- Pre-revenue testing, then revenue service testing. Both come before the June opening.
- 2027 how-to-ride outreach. Virtual and in-person sessions on trip planning, paying fares, reading signs and loading bikes onto trains and buses.
- Saturday, June 12, 2027. Passenger service begins.
Staffing is ramping up alongside the testing. Metro Transit plans more than 1,400 positions to support the existing and extended lines, including train operators, maintenance staff, police and TRIP agents. About 260 were still open at the time of the October council briefing.
In Eden Prairie, the line meets the street in four places
Large stretches of the line through Eden Prairie run on bridges. One example is the viaduct over Prairie Center Drive and Technology Drive, where a test train was seen curving around the Elevate residential complex toward SouthWest Station on the afternoon of the September celebration. The line also comes down to street level at four at-grade crossings, out of 14 on the whole extension, according to Eden Prairie Local News.
| Crossing | Landmark nearby |
|---|---|
| Technology Drive at Flying Cloud Drive | Costco and Asia Mall |
| Town Center Drive | Redstone American Grill |
| Viking Drive stub off Flying Cloud Drive | Holiday Inn and Marriott hotels |
| West 70th Street | Golden Triangle |
Technology Drive is the busiest of the four. State records counted 11,640 vehicles a day there in 2024. That makes the Costco and Asia Mall run the place where most Eden Prairie drivers will see a light-rail gate drop before they ever see a train stop at a platform. Project outreach manager David Davies called the Technology Drive crossing one of the project's highest priorities. He said it could get more signage and an in-person presence once regular service begins.
What the gates do during testing
Crossing behavior during testing can surprise people who learned to read freight crossings. When testing began, the City of Eden Prairie warned that tests would activate the lights, bells and gates at road and trail crossings. The signals and gates could activate even when no train was in sight, and the city told everyone to obey them anyway. The trains can also move in either direction on either track, according to Eden Prairie Local News coverage of the first week of testing. A train coming from the "wrong" side is normal here.
The test cars carry the message on their sides. According to Eden Prairie Local News, one was wrapped in traffic-barrier graphics reading "Never try to beat a train! Stop when flashing! Listen up!" Another read "STAY SAFE" and "OPENS IN 2027."
The project's plans for this phase include variable message signs at Technology Drive and at Bren Road in Minnetonka, pedestrian signage at trail crossings where needed, and Metro Transit Police posted at crossings during testing work. The Eden Prairie Police Department will assist on request. Mailings have gone to residents within a couple of square miles of the corridor. "These folks are not used to seeing trains operating on a regular basis on these tracks," Davies said, according to Eden Prairie Local News. The outreach team is also contacting every school district along the alignment, with presentations tailored to students. City updates on the testing and operator training go out through the city website, its social channels and the Life in the Prairie newsletter.
Four stations, each next to somewhere you already go
The crossings come first, and the stations follow in June. The city's station page lists all four:
- City West sits beside Optum's corporate campus near Highway 62, a bit east of Shady Oak Road, and connects to a park-and-ride lot. Optum donated the land for the station and its pedestrian walkways.
- Golden Triangle has a single center platform that serves trains in both directions, with access from the adjacent park-and-ride lot and West 70th Street. The city says the surrounding area holds nearly 10 million square feet of industrial and office space.
- Eden Prairie Town Center sits just west of Eden Prairie Center, with multifamily housing to the south and east along Singletree Lane.
- SouthWest combines the trains with SouthWest Transit buses on a shared platform, with an expanded park-and-ride. Purgatory Creek Park is close by.
Once service starts, the line will run 25.5 miles as a single Green Line. From SouthWest Station, riders can go to Union Depot in St. Paul, or change to the Blue Line at Target Field Station for the airport and Mall of America. Every station on the extension will have emergency call buttons, security cameras and "Text for Safety" signs that connect riders to dispatchers.
The bus connections are being finalized in the same months
The bus routes feeding the stations are being settled during the same stretch of testing. Metro Transit's Network Now 2026 amendment, released August 25, proposed changes to Routes 9, 30, 36, 38, 46, 615, 705, 716, 757 and 758. It also added a new Route 617 that would connect to the Green Line and extended Route 615 to Opus. Public comment ran from August 25 through October 4. The revised plans were scheduled to go to the Met Council for adoption in November, according to the Sun Sailor.
At the September 26 celebration, Green Line Extension outreach coordinator James Mockovciak, who has worked on the project for nearly 12 years, said "the system is basically 98% completed," according to Eden Prairie Local News. What remains is the systems testing that runs through December and the pre-revenue testing after it. Until June 12, the clearest sign of it on Eden Prairie's streets will be the gates coming down on Technology Drive.
If you'd like to talk about what the June opening could mean for a home near City West, Golden Triangle, Town Center or SouthWest Station, Local Roots Real Estate is glad to walk through it with you, street by street. Request a Free Home Valuation & Neighborhood Consultation and we'll share what we see along the line.